Collision Equipment Experts located in Elgin, Illinois has been chosen to provide the equipment, installation and service for the Akzo Nobel Training Center in Lombard, Illinois. The State of the Art center will feature an Ultra Plus Spray Booth with Advance Cure, Ultra Paint Mix Room and a Sanding Station manufactured by Global Finishing Solutions. Additional equipment includes an Eurovac Dust Collection System, Atlas-Copco Full Feature Compressor, TransAir air piping and Martech breathable air system.

AkzoNobelFrontView.jpg
Training Center Equipment Front View

Training Center Layout.jpg
Training Center Layout

November 2006: The equipment shipments arrive.

AkzoNobelShipment2.jpg
Spray Booth Equipment Arrives

AkzoNobelShipment2.jpg
More Of The Shipment

December 4th, 2006: The Paint Booth and Sanding Station pit work begins.

AkzoNobelConcreteWork2.jpg
Pit Excavation Begins

AkzoNobelConcreteWork2.jpg
More Pit Excavation

AkzoNobelPit7.jpg
Sanding Station Pit Ready For Second Pour

AkzoNobelPit7.jpg
Spray Booth Pit Ready For Second Pour

December 11th, 2006: Equipment Installation Begins

AkzoNobel014.jpg
Completed Spray Booth Pit

AkzoNobel015.jpg
Completed Sanding Station Pit

 December 18th, 2006: Building Construction Begins

AkzoNobel017.jpg
Reworking The Sprinkler System

AkzoNobel017.jpg
Partition Wall Going Up

December 26th, 2007: Construction Continues

AkzoNobel021.jpg
Upgrade The Electric Service

AkzoNobel021.jpg
Erection of The Sanding Station Continues

January 2, 2007: The equipment installation continues.

AkzoNobel023.jpg
The partition wall is ready for paint.

AkzoNobel023.jpg
The paint mix room is up.

January 8, 2007: The installation is progressing
.

AkzoNobel026.jpg
Rick Farnan from Akzo Nobel reviews the progress with Joe Conti from Collision Equipment Experts

AkzoNobel026.jpg
Mechanical Room, Sanding Station, Paint Mix Room and some of the Ultra Plus Booth are up.

December 15th 2007: Getting Much Closer

AkzoNobel030.jpg
Air Compressor, Dust Collection and Breathable Air Systems In Place

AkzoNobel030.jpg
Ultra Plus Booth Is Almost Completed

AkzoNobel030.jpg
Hallway Door and Booth Cabin Going Up

January 22, 2007: Construction is winding down.

AkzoNobel036.jpg
Wall around sprinkler system getting mud.

AkzoNobel036.jpg
The walls are getting painted.

AkzoNobel036.jpg
Preparation for the suspended ceiling.

AkzoNobel036.jpg
Installation of the suspended ceiling tiles.

January 29, 2007: Nearing Completion

AkzoNobel041.jpg
Sprinklers Getting Completed

AkzoNobel041.jpg
Dust Collection Drop With Air

AkzoNobel041.jpg
Sanding Station Ready For Filters

February 5, 2007: Inspections and Approvals

AkzoNobel043.jpg
Roll Up Door Installed, Painting is Almost Complete.

AkzoNobel043.jpg
Waiting For Inspections From The Local Jurisdiction.

February 12,2007: Nearing Completion

AkzoNobel045.jpg
Global Finishing Solutions Equipment Mechanical Installation Completed

AkzoNobel045.jpg
Collision Equipment Experts Service Technicians Installing Booth Filters

February 19th, 2007: Working on the Electric Upgrade

AkzoNobel047.jpg
Pulling Wires For The New Breaker Box

AkzoNobel047.jpg
New Main Electric Box

February 26, 2007: Electric Work Continues

AkzoNobel049.jpg
New Switch Box In Place

AkzoNobel049.jpg
Special Sound Deading Material In Place

March 12, 2007: The Electric Work Continues.

AkzoNobel050.jpg
Main Electric Service Box Upgrade

April 9, 2007: Waiting on Approval.

AkzoNobel051.jpg
Waiting on Electric Approval

April 23, 2007: Moving Again.

EurovacCollector.jpg
Eurovac Dust Collection Collector

Equipment Room.jpg
Equipment Room

Sanding Station.jpg
Sanding Station With Dust Collection Drops

Training Center.jpg
Floor Tile Finished

Air Drops.jpg
Air Line Drops

Ultra Plus 1 Booth.jpg
Ultra Plus 1 Booth With Air Drops

Training Center.jpg
Training Center With Floor Tile Completed

June 4,2007: Equipment Start Up Completed

AkzoNobel057.jpg
Sergio Programing The Booth Control Panel

June 18, 2007: The Work Is Complete, Waiting On Final Inspection.

AkzoNobel079.jpg
Atlas Copco Compressor and Eurovac Dust Collection

AkzoNobel079.jpg
Ultra Plus and Advance Cure Control Panels

AkzoNobel079.jpg
Walkway Between The Booth and Paint Mix Room

AkzoNobel079.jpg
Sanding Station

AkzoNobel079.jpg
Paint Mix Room

AkzoNobel079.jpg
Ultra Plus 1 Spray Booth

AkzoNobel079.jpg
Training Center Completed

AkzoNobel079.jpg
Training Center Front View

AkzoNobel079.jpg
Equipment Room

AkzoNobel079.jpg
Atlas Copco Compressor and SATA Breathable Air

July 2nd, 2007: Occupancy Is Approved!

The Final Inspections Are Complete and Approved
AkzoNobel073.jpg
Competed Training Center

We would like to thank all of you for following along as we provide Akzo Nobel and their customers the most technologically advanced training center in North America.

We would also like to thank the following manufactures: Global Finishing Solutions, Eurovac, Atlas Copco, Goff Enterprises, Davies Supply, Transair, Sata and Becca.

A special thank you to a everyone at C&S Enterprises and all the contractors required to put this project together.

Collision Equipment Experts would like to thank Akzo Nobel for selecting us as their supplier for the equipment, installation services and equipment maintenance required to complete this project and keep the equipment operating at peak efficiency.

If you would like to have us assist you to improve operating efficiency, decrease operating costs or servicing your equipment, you can contact us at (847) 695-5800 or email:dputney@collisionequipmentexperts.com.